EasyProjects
Easy Projects is Work and Project Management Software that is designed to help teams of all sizes collaborate more effectively, stay on budget and deliver projects faster.
Birdview
Birdview PSA is a professional services automation platform built for organizations that want to better manage their entire delivery lifecycle. It includes all of the features and functionality of Easy Projects, plus an added layer of advanced functionality and financial tools for billing clients and tracking revenue and profit.
Project Management and Professional Services Automation
Easy Projects and Birdview blog

Learn how to manage projects efficiently. Tips and strategy from experts.
Stories & new approaches to project management, videos & training.

all articles
Project Management 101 & Tools

How to plan your project backwards from a deadline

Featured image

Sometimes you know when your project is supposed to be completed and need to work backwards to determine when you should start it. To do this you need to work with dependencies.

Dependencies are used when a set of tasks must be worked on and closed in a specific order. For example, if your project involved building a website for a client, you would need their content before you could go live with the site.
When you have a hard target end date (deadline) that cannot be delayed, and you want to figure out when you need to start the project, you’ll need to use the “Start to Finish” dependency. First, you’ll need to put your tasks in the right sequence order, and know the duration for each task. For the previous example, let’s assume that developing content for the website will take 5 days, and designing the website will take 2 days and our hard target end date is April 30 2012.
Tasks in order

Once we have our tasks laid out, we will state the end date of the Project (the deliverable date). Next we will place a “Start to Finish” dependency on all the corresponding tasks, working down up. As long as we place their end date, and the duration Easy Projects will auto-calculate their start dates.
dependency dialog

Starting with the 2nd last activity, it will depend on the last activity, and will continue all the way up the steps. If the end date needs to be changed, we can simply change that start date and end date, which will change all the other start/end dates in the sequence.
Full Schedule with dependencies
If there are other scenarios you’d like to see written about, please let us know.

Update: Changing the project end date now also updates your activity start and end dates, whether you have dependencies activated or not. Read all about the new feature here!